Hi guys,

I've been doing my driveway, basically removing a few hundred tonnes of dirt, levelling and then 8" of crushed concrete ready for a gravel finish. Been happy doing this myself but needed a brickie to build some piers.

Can you give me an idea on how many 4ft piers I can expect one brickie to build a day? there's about 108 bricks per pier. No labourer, but bricks are laid out next to each location.

Link to post
Share on other sites

Hey TomTom

A good brickie should be able to lay 1000+ bricks a day, but thats with a labourer. If he has to keep stopping to mix up more muck, then you might only be looking at half that figure.

So possibly, 5 peirs a day as a rough guess I'd say, or rent a mixer for

Link to post
Share on other sites
1,000 a day building piers? You're are hard taskmaster DIY Guy:D

No, sorry, thats 1000 a day under normal brick laying circumstances, such as walls. Doing peirs on his own, and having no labourer, around 500 a day would not be asking a lot.